Project Timeline
The timeline below offers a broad overview of the Whitechapel Central project, including proposed construction and refurbishment schedules. Visit our news and updates page for more details of current and upcoming works or to download the most recent local community newsletter.
2017
Oct
Demolition work began
Autumn 2017
2018
Apr
Planning Application Submitted
Spring 2018
Apr
Public Exhibition Events
Spring 2018
2019
May
Tower Hamlets Strategic Development Committee
Resolution to grant received from Committee Members
Sep
Decision Notice Issued
Approval Granted by Tower Hamlets
2020
Mar
Proposed Amendments
Information Session - Exhibition Boards available on website
Sep
Planning Committee for Amendments
Nov
First Residents Due to Move In
Winter 2020
2021
Jun
Final Residents Phase 1 due to Move In
Spring 2021